The solution to this project is a newly designed loading unit that is installed on standard container transport wagons. It uses the maximum permitted width of up to 3.1 meters as defined by the railway clearance profile and combines the structural separation of the wagon and the superstructure with an innovative use of eight container locking pins, four of which provide the necessary strength. This is made possible because the two halves of the unit are buffered against each other. As a result, the system can be designed more easily, transport significantly more weight than a conventional intermodal loading unit, and suitability for hump yard operations.
The working plan comprises six work packages. In the first step, the IML determines the detailed requirements of the use case, and Wecon designs the first prototype based on these requirements. This prototype undergoes internal static testing and is deployed by Captrain on a rail spur. The results are incorporated into modifications and the construction of a second prototype. At the same time, Fraunhofer IML is working with regulatory authorities to develop a testing protocol for rail certification, which will serve as the basis for classifying the unit as a “combined transport loading unit without road approval.”
The key steps of the project are:
- Development of detailed requirements for the use case
- Design and construction of the first prototype
- Development and testing of a test plan for railway certification
- Operational testing on a rail spur and hump yard testing at a test site
- Construction and testing of the second prototype with optimized specifications
- Scientific project management and dissemination
In May 2026, the first prototype was successfully tested on a rail spur and during a cross-border trip and received approval as a loading unit. A modified prototype will be built and tested in the second year of the project.